Springmoor Grange School will become home to students from the existing Ox Close Primary and Ox Close Nursery Schools.
The contractor behind the construction of a new primary school in Spennymoor, which will replace the existing Ox Close Primary and Ox Close Nursery Schools, has shared the latest images from the site as the project nears completion.
North of England contractor, Esh Construction, is working in partnership with Durham County Council to deliver a two-storey school that will open in September 2024 and have capacity for up to 630 pupils in addition to a nursery unit. The new school will be called Springmoor Grange School and will be located on the Durham Road site of the former Tudhoe Grange Comprehensive School.
Passers-by can see the latest progress externally, with brickwork, rainscreen cladding and curtain walling all substantially complete, allowing the perimeter scaffold to be taken down to reveal the new building. Photovoltaic (PV) panels have been installed on the roof which will allow the school to generate its own solar energy.
The fit-out internally, including first and second fix joinery, is well underway and will create 21 teaching classrooms, a nursery, learning community suite, library, office spaces, staff room, toilet facilities, changing rooms, hall, and dining and kitchen facilities. Fixed furniture is also being installed, including classroom kitchens.
First fix mechanical and electrical works are well advanced and over the coming weeks, the focus will be on finishes and decoration as Esh Construction moves towards final handover.
The site car park is complete and work is ongoing off Spennymoor’s Durham Road to form new entrances into the school.